Professional Construction Management |
From inside the book
Results 1-3 of 87
Page 101
Almost all jobs will require change a orders due to changes , drawing errors , and other modifications . A contingency allowance for changes and minor omissions should thus be developed so that an overall estimated cost at completion ...
Almost all jobs will require change a orders due to changes , drawing errors , and other modifications . A contingency allowance for changes and minor omissions should thus be developed so that an overall estimated cost at completion ...
Page 243
The Effects of Changes The effects of changes can be subdivided into three main categories : 1 Direct costs 2 Time ... and staff time that can be clearly attributed to work associated with a change or delay constitute direct costs .
The Effects of Changes The effects of changes can be subdivided into three main categories : 1 Direct costs 2 Time ... and staff time that can be clearly attributed to work associated with a change or delay constitute direct costs .
Page 397
ARTICLE 9 Changes in the Project 9.1 The Owner , without invalidating this Agreement , may order Changes in the Project ... 9.1.1 A Change Order is a written order to the Construction Manager signed by the owner or his authorized agent ...
ARTICLE 9 Changes in the Project 9.1 The Owner , without invalidating this Agreement , may order Changes in the Project ... 9.1.1 A Change Order is a written order to the Construction Manager signed by the owner or his authorized agent ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse