" Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change ; provided, however, that the Contracting Officer, if he decides that the facts... "
The Code of Federal Regulations of the United States of America - Page 103
1978
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 pages
...of whether, under the "Changes" article of the contract, plaintiff can escape the requirement that "Any claim by the contractor for adjustment under...by the contractor of the notification of change," and the requirement that any disputes concerning a question of fact resulting from the change shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

1978 - 1058 pages
...equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing accordingly....Officer, if he decides that the facts justify such Title 41 — Public Contracts, Property Management action, may receive and act upon any such claim...
Full view - About this book

The Code of Federal Regulations of the United States of America

1974 - 1020 pages
...shall be made in the contract price or delivery schedule, or both, and the contract shall be modifled In writing accordingly. Any claim by the Contractor...Contracting Officer, if he decides that the facts Justlf, such action, may receive and act upon any such claim asserted at any time prior to final payment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1964 - 1202 pages
...an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly....Contractor of the notification of change: Provided, howevtr. That the Contracting Officer, if he decides that the facts justify such action, may receive...
Full view - About this book

The Code of Federal Regulations of the United States of America

1978 - 880 pages
...performance or both, and (il) in such other provisions of the contract as may be so affected, and the contract shall be modified In writing accordingly....receipt by the Contractor of the notification of change: Profited, however, That the Contracting Officer, if he decides that the facts justify such action,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1977 - 944 pages
...paid to the contractor; and (3) In such other provisions of the contract as may be affected, and the contract shall be modified In writing accordingly....receipt by the Contractor of the notification of change: Prodded, however, That the Contracting Officer, It he decides that the facts justify such action, may...
Full view - About this book

The Code of Federal Regulations of the United States of America

1971 - 824 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...facts Justify such action, may receive and act upon an; such claim asserted at any time prior to final payment under this contract. Failure to agree to...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1955 - 1316 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...decides that the facts Justify such action, may receive ana act upon any such claim asserted at any time prior to final payment under this contract. Failure...
Full view - About this book

The Code of Federal Regulations of the United States of America

1969 - 256 pages
...Any claim by the contractor for adjustment under this clause must be asserted within thirty (80) days from the date of receipt by the contractor of the...that the facts Justify such action, may receive and 2-7.350-20 act upon any such claim asserted at any time prior to final payment under this contract....
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1991 - 550 pages
...other provisions of a contract, such as the requirement in the Changes clause of Standard Form 32, that any "claim by the contractor for adjustment under...by the contractor of the notification of change," are considered to be specifically required under the interpretation. (2) Indirect allocation of all...