GAO HEARING QUESTION 12 The GAO has noted that the Authority's schedule for beginning of service on the various system phases does not allow for "any time for delays due to lawsuits, strikes, and adverse weather". Please describe how this has been changed in the Authority's current startup estimates. The Authority has consistently been of the opinion that provision for unforeseen delays is counter-productive. best interest that all involved in the Metro construction feel the urgency of completing the program as soon as possible. Deliberately stre out the program will cause costs to increase due to escalation over which the Authority has no control. - a force Provision for 18 months delay has been recognized in the $4,650 million estimate for the E, F and K Routes. Also, the 15 percent or $467 million unfunded contingency should be adequate to provide for increased cost from any scurce. QUESTION 13 GAO HEARINGS In the May 9th Report to Senator Byrd the CAO discussed (on page 20 to 21) several specific contract cost overruns. Were these reflected in the $139.9 million increase noted in the August 1975 Office of Program Control Report. Yes, these items were included in cur August Report. A breakout of the specific items follows: GAO HEARING QUESTION 14 Are there now any delays or cost overruns which the staff foresees but which have not been publicly reported? If so, please submit a description of these for the record. The Authority's staff anticipates that the cost of construction inspection may exceed the amount programmed for this task, however there is no basis for quantifying this increase until a definite trend is firmly established. The staff also foresees an increase in the cost of insurance and possibly in the amounts of contract modifications. These potential cost increases will be closely monitored and the Congress will be advised of their impact when they can be quantified. The attached Table I to House D.C. Subcommittee Staff Analysis of Following our testimony, Mr. Gutmann and I were asked by press for comment on the $6.125 billion estimate, which of course we had not previously seen. Mr. Gutmann's qualified reply to "Well, could the cost go to $6.1 billion?" permitted the Post writer to associate GAO with the House figure. Herewith are brief comments on the main components of the House staff figures: 、 WMATA November 1974 estimate. The GAO May 8, 1975 report to Senator Byrd projected The GAO-Byrd report stated "route alignments currently route. The GAO-Byrd report concluded that WMATA escalation Source of this figure is unknown to WHATA. The GAO- Current Hearings before House D.C. Subcommittees .312 This figure is from the July 7, 1975 GAO report which The GAO-Byrd report recognized that recipients of the report would likely add all of the high projections and therefore cautioned: We believe it is reasonable to assume that some of Attachment as Jackson Graham |