Page images
PDF
EPUB

the weather was suitable, it was decided to widen the channel as far as the available funds would allow, about $2,500.

The amount expended up to June 30, 1885, was $32,000.

The work was completed in accordance with the approved project on August 7, 1884, and the appropriation is exhausted.

At the close of the work there was a channel with a minimum width of 210 feet and a depth of 8 feet at mean low water.

July 1, 18-4, amount available

July 1, 1885, amount expended during fiscal year, exclusive of outstanding liabilities July 1, 1884.

(See Appendix H 17.)

$2,498 32

2,498 32

18. Wicomico River, Maryland.—The natural channel of this river for some distance below the town of Salisbury was quite crooked and narrow, and at the shoalest places did not afford more than a few inches of water at low tide. Much injury had also been done by the saw-mills pouring their dust into it. A considerable portion of the shoals was found to be composed of water-soaked saw-dust mixed with mud and sand.

The project for improving this river was adopted in 1871, and had in view the giving a depth of 7 feet at mean low water in a channel about 70 feet wide for a distance of about 2 miles below the bridge at Salisbury. The project also included some dikes for the contraction of the water-way and as a place behind which to deposit material dredged from the channel.

Under the appropriation of $10,000 appropriated July 5, 1884, a contract was made for continuing work in accordance with the approved project, and the work is now being carried on and will probably be finished early in September.

This will give a channel of from 100 to 85 feet in width and a depth of 7 feet at mean low water, an extension of the original plan. Total amount expended to June 30, 1885, was $45,524.17.

Amount appropriated by act approved July 5, 1884..

July 1, 185, amount expended during fiscal year, exclusive of

outstanding liabilities July 1, 1884..

July 1, 1885, outstanding liabilities..

July 1, 1885, amount available................. (See Appendix H 18.)

$10,000 00

$3,500 83
2,021 01

5,521 84

4,478 16

19. Upper Thoroughfare between Deil's Island and the mainland.-At its eastward end this passage is an arm of Tangier Sound, of considerable width, narrowing and shoaling rapidly, and exposed to southwest storms. The Maryland Steamboat Company, running from Baltimore, have a pier at Deil's Island.

The original plan was for dredging a harbor and making a protecting breakwater, and the estimate for the same was $20,000.

July 1, 1884, amount available

July 1, 1885, amount expended during fiscal year, exclusive of outstanding liabilities July 1, 1884.....

July 1, 1885, amount available......

Amount (estimated) required for completion of existing project.....
Amount that can be profitably expended in fiscal yearending June 30, 1-87
Submitted in compliance with requirements of section 2 of river and
harbor acts of 1966 and 1×67.

(See Appendix H 19.)

$4,810 26

140 35

4,669 91

15,000.00 15,000 00

20. Removing sunken vessels or craft obstructing or endangering navigation. Two sunken barges were reported on January 6, 1885, as being near Grove Point and in way of vessels going up the bay to Chesapeake and Delaware Canal.

An examination was ordered to ascertain if the wrecks caused such obstruction to navigation as is contemplated by section 4 of the river. and harbor act of June 14, 1880.

Two attempts were made to make the examination, but failed on account of ice in the Chesapeake Bay. Finally, on the 7th of April, 1885 an examination was made from the steamer Fish Hawk, loaned by the U. S. Fish Commission, and the barges were found to have sunken to a safe depth and no longer dangerous.

(See Appendix H 20.)

EXAMINATIONS AND SURVEYS FOR IMPROVEMENTS, TO COMPLY WITH REQUIREMENTS OF THE RIVER AND HARBOR ACT OF JULY 5,

1884.

The following locality was examined by the local engineer in charge, and not recommended for improvement:

1. Harbor at Easton Point, commencing at a point on Third Haven River where the Government work on the channel of said river was recently suspended. The report on this examination was transmitted to Congress and printed in House Ex. Doc. No. 71, Forty eighth Congress, second session. (See also Appendix H 21.)

And it appearing, after preliminary examination by the local engineer, that the localities were worthy of improvement by the General Government, Mr. Smith was charged with and completed the following, the results of which were transmitted to Congress and printed:

1. Lewes Creek and Rehoboth Bay, Delaware, Assateague and Chincoteague bays, Maryland, with a view to form continuous inland navigation from Chincoteque Bay, in Virginia, to Delaware Bay, at or near Lewes, Delaware.-Printed in House Ex. Doc. No. 107, Forty-eighth Congress, second session. (See also Appendix H 22.)

2. Pocomoke River and Sound, Maryland.-Printed in House Ex. Doc. No. 186, Forty-eighth Congress, second session. (See also Appendix H 23.)

3. Skipton Creek, Maryland.-Printed in House Ex. Doc. No. 192, Forty-eighth Congress, second session. (See also Appendix II 24.) Reports submitted for the following localities will be found appended to this report as follows:

4. Tuckahoe Creek, Maryland. (See Appendix H 25.)

5. Sassafras River, Maryland, above Georgetown. (See Appendix H 26.)

IMPROVEMENT OF PATAPSCO RIVER AND CHANNEL TO BALTIMORE,

MARYLAND.

Officer in charge, Lieut. Col. W. P. Craighill, Corps of Engineers. Channel to Baltimore, Maryland.-The depth in this channel has been by successive steps increased from 17 feet at mean low water to 27 feet, with an average rise of tide of about 18 inches.

The project of improvement at first adopted and commenced in Oc

tober, 1853, had for its object to give a channel 22 feet deep at mean low water, with a width of 1 0 feet.

Little was done before the late war, but afterwards these dimensions were increased, a depth of 24 feet at mean low water being determined upon, with a width of channel ranging from 250 to 400 feet. This chan nel was completed in 1874, important changes of position having been given to a portion of it by which the distance was materially lessened and the expense of maintenance decreased.

The object of the improvement was to permit the approach to Baltimore at mean low water of vessels drawing from 224 to 23 feet, and at ordinary high water of vessels drawing 24.and 243 feet.

The last appropriation previous to 1884 was in August, 1882, $450,000, there being none in 1883. This was expended in giving a depth of 27 feet in the Fort McHenry, Brewerton, and Craighill branches of the channel, and in the "cut-off" between the Brewerton and Craighill branches, by which last a saving of nearly a mile in distance was made, besides an improvement in direction and diminution in cost of maintenance. The width attained was, however, too little.

The work of 1883 greatly exceeded what was ever accomplished in one year before, and probably more of its kind than was ever executed at any other locality in the United States in a single year. The large amount of 3,083,804 cubic yards of material was removed.

At the end of the fiscal year, June 30, 1884, the widths in the several divisions of the channel were as follows:

Fort McHenry to Fort Carroll, 250 feet; Brewerton Channel to cutoff, 250 feet; cut-off to Craighill Channel, 225 feet, except for a space of one-half mile in length in the central portion, where it was but 160 feet wide; Craighill Channel, 200 feet wide.

But little was done in the first half of 1884, for want of money. The improvement was vigorously pushed during the remaining portion of the working season of 1884 and in 1885. It is a very fortunate circumstance that the material through which the channel has been excavated has been for the most part quite soft and yielding, so that if a vessel happens to touch the sides of it she need not suffer serious damage unless she be moving at too great speed or be very carelessly handled.

The following are the widths of the respective branches of the channels June 30, 1885, with a depth of 27 feet at mean low water:

[blocks in formation]

Though the depth of 27 feet at low water has been reached and seems to suffice for present needs, the width is too little for easy or safe navigation by very large vessels whose length is considerably greater than the width of the channel.

Up to June, 1884, the United States had expended $2,084,489.12 with the results indicated above. The city of Baltimore and the State of Maryland, chiefly the former, had contributed to the same object $584,000.

Dredging was suspended June 30, 1885, owing to the failure of Congress to appropriate at the last session. The balance available must be held in hand for use in case of an emergency. Advantage has been taken of this absence of dredges to make a thorough resurvey of the whole channel. The results of this survey are not yet ready, but will be submitted in a special report if necessary.

July 1, 1884, amount available

Amount appropriated by act approved July 5, 1884

July 1, 1885, amount expended during fiscal year, exclusive of outstanding liabilities July 1, 1884 .....

July 1, 1885, amount available

$70,463 65

250,000 00

320,463 65

289,617 24

30, 46 41

200,000 00

(Amount (estimated) required for completion of existing project. Amount that can be profitably expended in fiscal yearending June 30, 1887 200,000 00 Submitted in compliance with requirements of section 2 of river and harbor acts of 1866 and 1867.

(See Appendix I.)

IMPROVEMENT OF THE HARBORS AT WASHINGTON AND GEORGETOWN, DISTRICT OF COLUMBIA-IMPROVEMENT OF THE POTOMAC RIVER AT WASHINGTON, DISTRICT OF COLUMBIA-IMPROVEMENT OF JAMES RIVER, VIRGINIA, AND OF SHENANDOAH RIVER, WEST VIRGINIA.

Officer in charge, Maj. Peter C. Hains, Corps of Engineers.

1. Harbors at Washington and Georgetown, District of Columbia.-The improvement of the harbors at Washington and Georgetown was first undertaken by the Government in 1870. Prior to that time the channel over the bar below Georgetown had only 8 feet of water at mean low tide. It was crooked, narrow, and difficult to navigate, so much so that up to 1870 the corporation of Georgetown had itself spent considerable money in dredging it. The bar below Long Bridge was less troublesome and somewhat deeper, but did not satisfy the wants of commerce. The Washington Channel or harbor, along the city front, from the northern limit of the arsenal to Long Bridge had a ruling depth of only 10 feet at mean low tide. There were, besides, in the harbor of Georgetown many projecting rocks with a depth of water over them that rendered navigation difficult and dangerous.

The original project looked to securing a depth of 16 feet at low tide to Georgetown and along the wharves of the Washington Harbor from Arsenal Point to Long Bridge, and the removal of the most dangerous rocks that obstructed navigation in the harbor of Georgetown. When by act of August 2, 1882, Congress made an appropriation for improving the Potomac River in the vicinity of Washington, D. C., having reference to the improvement of navigation, the establishment of the harbor lines, and the raising of the flats, the project was modified and limited to the removal of rocks in Georgetown Harbor to the depth of 20 feet at mean low tide, that being the depth to be given to the channel below under the late act. For the last two and a half years work has been carried on under the amended project. The total amount that has been expended on the improvement of Washington and Georgetown harbors up to the close of the fiscal year ending June 30, 1885, is $272,923.25; of this amount $249,505.28 was expended on dredging the approaches to Georgetown Harbor and the Washington Channel; the remainder was expended in the removal of rocks in Georgetown Harbor. At that time there was full 20 feet of water at mean low tide in the harbor at Georgetown, except in certain places where projecting points of rocks had been found.

During the past fiscal year operations have been directed to the removal of the projecting rocks. The work has been done by contract. During the year $15,072.48 has been expended; ten rocks have been

removed, and the removal of the others is being carried on under contract.

No additional appropriation is asked for this work.

July 1, 1884, amount available..

July 1, 1885, amount expended during fiscal year, exclusive of

outstanding liabilities July 1, 1884.

July 1, 1885, outstanding liabilities..

July 1, 1885, amount available...... (See Appendix J 1.)

$34,084 78

$15,072 48
586 63

5,659 11

18,425 67

2. Potomac River at Washington, District of Columbia.-The project for the improvement of the Potomac River in the vicinity of Washing ton, D. C., was adopted by act of Congress passed August 2, 1882, and has for its object the improvement of the navigation of the river by deepening and widening its channels so as to accommodate vessels of the largest class that can reach Giesboro' Point; the establishment of harbor lines beyond which no obstructions, such as wharves, &c., should be built, and at the same time to fill and raise the marshes or flats in front of the city above overflow by the highest freshets, the material taken from the river in deepening and widening the channel to be used in filling the flats.

Before the improvement was commenced the flats or marshes in front of the city had become so offensive that certain parts of the city in their neighborhood were not habitable. The channel to Georgetown was narrow and crooked, and had not sufficient depth to accommodate vessels trading to that port; the Washington Channel leading to the wharves along the front of the city, between Long Bridge and the site of the arsenal, was also inadequate to the wants of commerce. Vessels drawing 16 feet frequently grounded in the Georgetown Channel, and that depth was only maintained by frequent dredging.

The expenditures for the improvement have thus far amounted to $532,445.22, and have given a channel from Giesboro' Point to Georgetown 20 feet deep at low tide, and over 300 feet wide, and a partially completed channel along the Washington Channel of the same depth. In addition, about 2,400,000 cubic yards of filling, including embank ment, have been deposited on the flats, raising above overflow by mean high tide about 225 acres of marsh land. A temporary embankment has been built along each side of the sewer canal to prevent the sewage discharged into it from spreading out over the flats, and to enable the flats on each side of it to be filled with the material taken from the Virginia Channel. About 15,000 linear feet of embankment have been built along the margins of Sections I, II, and III, with a riprap footing of loose stone. About 6,000 linear feet of similar embankment have been built along the margin of the large tidal reservoir. The work has been done chiefly by contract, after public advertisement for proposals. The method adopted at first was to dredge the material from the riverbed, convey it in scows to a receiving basin, and there dump it, then redredge it, deposit it in cars, and carry it to the fiual dumping-ground on the flats. This method necessitated handling the material twice, and much of it had to be lifted a total vertical height of 60 to 70 feet before it was dropped on the dump. The plan now employed is to suck up the ma terial from the bed of the river by means of a centrifugal pump and discharge it through pipes connected by rubber cylinder joints. The vehicle used to convey the solid material is water, and the dredge built on this principle is called hydraulic. The material forming the bed of

« PreviousContinue »