Modification in the proposed arrangements for the Clinch River Breeder Reactor Demonstration Project: hearings before the Joint Committee on Atomic Energy, Congress of the United States, Ninety-fourth Congress, second session ... April 14 and 29, 1976U.S. Government Printing Office, 1976 - 524 pages |
From inside the book
Results 1-5 of 98
Page 19
... obligation called for by the original memorandum , except that there will not be any direct contractual obligation between AEC and BRC . The original memorandum provided that AEC and BRC would enter into a contract whereby BRC would : 1 ...
... obligation called for by the original memorandum , except that there will not be any direct contractual obligation between AEC and BRC . The original memorandum provided that AEC and BRC would enter into a contract whereby BRC would : 1 ...
Page 30
... obligation not to spend funds or intentionally incur contractual commitments exceeding the limitation in the agreements . The clear inference is that , in the absence of willful misconduct or bad faith on the part of an officer or ...
... obligation not to spend funds or intentionally incur contractual commitments exceeding the limitation in the agreements . The clear inference is that , in the absence of willful misconduct or bad faith on the part of an officer or ...
Page 42
... obligations of any of the parties under the Principal Project Agreements . " Other sections , particularly 2.1 and ... obligation to take these actions . Therefore , section 2.3.6 could have the effect of negating AEC's powers under ...
... obligations of any of the parties under the Principal Project Agreements . " Other sections , particularly 2.1 and ... obligation to take these actions . Therefore , section 2.3.6 could have the effect of negating AEC's powers under ...
Page 52
... obligations under the con- tract . However , under AEC procurement regulation ( AECPR ) 9-7.5006-9 ( e ) ( 16 ) , all costs incurred in connection with prosecuting claims against , or contesting actions of the United States are ...
... obligations under the con- tract . However , under AEC procurement regulation ( AECPR ) 9-7.5006-9 ( e ) ( 16 ) , all costs incurred in connection with prosecuting claims against , or contesting actions of the United States are ...
Page 57
... obligations for sharing project costs . Therefore , we believe AEC should consider the desirability of either ( 1 ) ... obligation under section 11.5 or ( 2 ) modify- ing the proposed contract among AEC , PMC , TVA , and Common- wealth to ...
... obligations for sharing project costs . Therefore , we believe AEC should consider the desirability of either ( 1 ) ... obligation under section 11.5 or ( 2 ) modify- ing the proposed contract among AEC , PMC , TVA , and Common- wealth to ...
Other editions - View all
Common terms and phrases
Accounting additional AEC's amended Appendix applicable appropriate approval Atomic Energy Breeder Reactor Corporation Chairman clause Clinch River Commission commitments Commonwealth Edison Company construction contractors Coop Cost Accounting Standards CRBR criteria Davis-Bacon Act decision DEMBLING Director Elec employees ERDA's expenses facilities Fast Breeder Reactor Federal Government hereinafter incurred indemnity Joint Committee Justification Data labor surplus area liability licensing LMFBR Demonstration Plant manage the project matter ment minority business enterprises Modification negotiated Nuclear Regulatory Commission obligations Office operation organization participation parties payment performance personnel PMC Board PMC's Principal Project Agreements Project Activities Project costs Project Management Corporation proposed contract pursuant to paragraph reactor manufacturer Reference Design Representative Moss request Research and Development respect responsibility revised Secretary of Labor Senator MONTOYA small business concerns special nuclear material specific subcontracts submitted Tennessee Valley Authority tion TVA's Utility Contribution Agreements utility industry