(a) The initial Procurement Request shall reflect the total estimated cost of the cost-sharing contract. The face page of the contract award shall indicate the total estimated cost of the contract, the Contractor's share of the cost, and the Government's share of the cost.

(b) The manner of cost-sharing and how it is to be accomplished shall be set forth in the contract. Additionally, contracts which provide for cost-sharing shall require the contractor to maintain records adequate to reflect the nature and extent of their costsharing as well as those costs charged the Agency. Such records may be subject to an Agency audit.

[61 FR 14505, Apr. 2, 1996] 1516.307 Contract clauses.

(a) The Contracting Officer shall insert the clause in 1552.216-71, Date of Incurrence of Cost, in cost-reimbursement contracts when an anticipatory cost letter has been issued on the project.

(b) The Contracting Officer shall insert the clause at 1552.216-74, Payment of Fee, in solicitations and contracts where a cost-reimbursement term form contract is contemplated, unless the Contracting Officer determines that such a provision would be detrimental to ensuring proper contract perform

ance.

(c) The Contracting Officer shall insert a clause substantially the same as 48 CFR 1552.216-76, Estimated Cost and Cost-Sharing, in solicitations and contracts where the total incurred costs are shared by the contractor on a straight percentage basis. The Con

48 CFR Ch. 15 (10-1-01 Edition)

tracting Officer may develop other clauses, as appropriate, following the same approach, but reflecting different cost-sharing arrangements negotiated on specific contract actions.

[49 FR 8852, Mar. 8, 1984, as amended at 56 FR 43711, Sept. 4, 1991; 61 FR 14505, Apr. 2, 1996; 61 FR 57338, Nov. 6, 1996]

1516.370 Solicitation provision.

The solicitation document shall state whether any cost-sharing is required, and may set forth a target level of cost-sharing. Although technical considerations are normally most important, the degree of cost-sharing may be considered in a selection decision when cost becomes a determinative factor in a selection decision.

[61 FR 14505, Apr. 2, 1996]

[blocks in formation]

1516.404-273 Limitations.

(a) No award fee may be earned if the Fee Determination Official determines that contractor performance has been satisfactory or less than satisfactory. A contractor may earn award fee only for performance rated above satisfactory or excellent. All award fee plans shall disclose to offerors the numerical rating necessary to be deemed "above satisfactory" or "excellent" for award fee purposes.

(b) The base fee shall not exceed three percent of the estimated cost of the contract, exclusive of the fee.

(c) Unearned award fee may not be carried forward from one performance

[blocks in formation]

1516.405 Contract clauses.

(a) The Contracting Officer shall insert the clause at 1552.216-70, Award fee (May 2000), in solicitations and contracts where a cost-plus-award-fee contract is contemplated.

(b) The Contracting Officer shall insert the clause at 1552.216-75, Base Fee and Award Fee Proposal (SEPT 1995), in all solicitations which contemplate the award of cost-plus-award-fee contracts. The Contracting Officer shall insert the appropriate percentages.

[60 FR 43404, Aug. 21, 1995, as amended at 64 FR 3876, Jan. 26, 1999; 65 FR 31500, May 18, 2000]

Subpart 1516.5-IndefiniteDelivery Contracts

1516.505 Contract clauses.

(a) The Contracting Officer shall insert the clause in 1552.216-72, Ordering-By Designated Ordering Officers, in indefinite delivery/indefinite quantity type solicitations and contracts.

(b) The Contracting Officer shall insert the clause in 1552.216-73, Fixed Rates for Services-Indefinite Delivery/ Indefinite Quantity Contract, in solicitations and contracts to specify fixed rates for services.

[blocks in formation]

1516.603-1 What is a Notice to Proceed?

(a) A Notice to Proceed (NTP) is a type of letter contract issued pursuant to FAR 16.603 under which an EPA Federal Classification Series 1102 (FCS) contracting officer or a duly authorized EPA on-scene coordinator with delegated procurement authority may initiate, in certain defined situations and subject to certain limitations and conditions, contracting actions to respond to certain situations as described in CERCLA section 104(a)(1) (42 U.S.C. 9604(a)(1)) and the Clean Water Act sections 311(c)(2) and (e)(1)(B) (33 U.S.C. 1321(c)(2) and (e)(1)(B)). An NTP may be utilized as a contractual instrument for certain

(1) Actions that EPA is authorized to undertake under CERCLA section 104(a)(1), 42 U.S.C. 9604(a)(1), and the National Oil and Hazardous Substances Pollution Contingency Plan (40 CFR part 300), to respond to situations where any hazardous substance has been released or there is a substantial threat of such a release into the environment, or there is a release or substantial threat of release into the environment of any pollutant or contaminant which may present an imminent and substantial danger to the public health or welfare, and

(2) Actions that EPA is authorized to undertake under sections 311(c)(2) and (e)(1)(B) of the Clean Water Act, 33 U.S.C. 1321(c)(2) and (e)(1)(B), and the National Oil and Hazardous Substances Pollution Contingency Plan (40 CFR part 300), to respond when there is a discharge, or a substantial threat of a discharge (to or upon navigable waters, adjoining shorelines, the contiguous zone, or natural resources belonging to, appertaining to, or under the exclusive management of the United States), of oil or a hazardous substance from a vessel, onshore facility, or offshore facility that is a substantial threat to the public health or welfare. Pursuant to a class Justification For Other Than Full and Open Competition executed

under the authority of FAR 6.302-2 and 6.303-1(c), an NTP may be issued on a non-competitive basis.

(b) What do subsections 1516.603-1 and 1516.603-2 cover? EPAAR 1516.603-1 and 1516.603-2 contain information and procedures relating to issuance and definitization of an NTP. An NTP is subject to, and must comply with, the applicable requirements for letter contracts in FAR 16.603 and the requirements in this section, and be definitized by an EPA FCS 1102 contracting officer.

[66 FR 12900, Mar. 1, 2001]

1516.603-2 What are the requirements for use of an NTP?

(a) An EPA FCS 1102 contracting officer or a duly authorized EPA on-scene coordinator with a delegation of procurement authority may issue an NTP so long as it does not exceed the limits of his or her procurement authority and only when all of the following conditions have been met:

(1) A written determination has been made by the Federal on-scene coordinator that

(i) As authorized by and consistent with CERCLA section 104(a)(1), 42 U.S.C. 9604(a)(1), and the National Oil and Hazardous Substances Pollution Contingency Plan (40 CFR part 300), the EPA must take action to respond to a hazardous substance release or substantial threat of such a release into the environment, or a release or substantial threat of a release into the environment of any pollutant or contaminant which may present an imminent and substantial danger to the public health or welfare, or

(ii) As authorized by and consistent with the Clean Water Act sections

311(c)(2) and (e)(1)(B), 33 U.S.C. 1321(c)(2) and (e)(1)(B), and the National Oil and Hazardous Substances Pollution Contingency Plan (40 CFR part 300), the EPA must take action to respond to a discharge, or a substantial threat of a discharge (to or upon navigable waters, adjoining shorelines, the contiguous zone, or natural resources belonging to, appertaining to, or under the exclusive management of the United States), of oil or a hazardous substance from a vessel, offshore facility, or onshore facility that is of such

a size and character as to pose a substantial threat to the public health or welfare of the United States; and

(2) Before a duly authorized EPA onscene coordinator with a delegation of procurement authority may issue an NTP, he or she must confirm that an EPA FCS 1102 contracting officer is not available to provide the required contracting support by the time the Federal on-scene coordinator requires the response action to be undertaken; and

(3) A written determination is made by an EPA FCS 1102 contracting officer or a duly authorized EPA on-scene coordinator with a delegation of procurement authority that there is no other existing contracting mechanism available to provide the required contracting support by the time required, including the inability of an existing emergency response contractor or other existing contract vehicle to respond in the required time frame. These conditions, as well as any other requirements applicable to NTPs or letter contracts contained in the FAR or EPAAR, must be met before an NTP can be issued by an EPA FCS 1102 contracting officer or a duly authorized EPA on-scene coordinator with a delegation of procurement authority.

(b) What should be included in an NTP? (1) Since an NTP is a type of letter contract, it is subject to the requirements of FAR 16.603. All of the relevant requirements of FAR 16.603 apply to NTP's including FAR 16.603-2, 16.603-3, and 16.603-4, and an NTP will include all appropriate FAR and EPAAR contract clauses. An NTP should also include an overall price ceiling and be as complete and definite as possible under the circumstances. To the extent NTPs require modification of any FAR or EPAAR prescribed procedures or clauses, an appropriate FAR or EPAAR deviation will be prepared.

(2) The EPA FCS 1102 contracting officer or duly authorized EPA on-scene coordinator with a delegation of procurement authority shall include in each NTP the clauses required by the FAR or EPAAR for the type of definitive contract contemplated and any additional clauses known to be appropriate for it. In addition, the following

clauses must be inserted in the solicitation (if one is issued) and the NTP when an NTP is used:

(i) The clause at FAR 52.216-23, Execution and Commencement of Work, except that the term on-scene coordinator may be used in place of the term contracting officer;

(ii) The clause at FAR 52.216-24, Limitation of Government Liability, with dollar amounts completed in a manner consistent with FAR 16.603-2(d); and

(iii) The clause at FAR 52.216-25, Contract Definitization, with its paragraph (b) completed in a manner consistent with FAR 16.603-2(c) or any applicable FAR deviation. The clause at FAR 52.216-26. Payment of Allowable Costs Before Definitization, shall also be included in a solicitation (if one is issued) and NTPs if a cost-reimbursement definitive contract is contemplated.

(3) Each NTP shall, as required by the clause at FAR 52.216-25, Contract Definitization, contain a negotiated definitization schedule that includes:

(i) Dates for submission of the contractor's price proposal, required cost and pricing data, and if required, make-or-buy and subcontracting plans; (ii) The date for the start of negotiations; and

(iii) A target date for definitization which shall be the earliest practicable date for definitization (an NTP must be definitized by an EPA FCS 1102 contracting officer). The schedule will provide for definitization of the NTP within 90 calendar days after the date of the NTP award. However, the EPA FCS 1102 contracting officer may, in extreme cases and according to agency procedures, authorize an additional period. If, after exhausting all reasonable efforts, the EPA FCS 1102 contracting officer and the contractor cannot negotiate a definitive contract because of failure to reach agreement as to price or fee, the clause at 52.216-25 requires the contractor to proceed with the work and provides that the contracting officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to appeal as provided in the Disputes clause.

(4) The maximum liability of the Government inserted in the clause at 52.216-24, Limitation of Government Liability, shall, as approved by the official who authorized the NTP, be the estimated amount necessary to cover the contractor's requirements for funds to complete the work to be performed under the NTP. However, it shall not exceed the estimated cost of the definitive contract.

(c) Are there any financial or monetary limitations on the use of an NTP? In addition to the requirements for issuance of an NTP set forth elsewhere in this subpart

(1) The total definitized dollar value of an individual NTP shall not exceed $200,000.00, and

(2) The applicable Program Office must commit and make available appropriate funding for the emergency response action taken under the NTP prior to NTP issuance.

(d) Are there any other procedural requirements for issuance of an NTP? An NTP must be issued in writing by the EPA FCS 1102 contracting officer or the duly authorized EPA on-scene coordinator with a delegation of procurement authority using a Standard Form 33. In addition, the EPA FCS 1102 contracting officer or the EPA on-scene coordinator awarding the NTP must ensure that the NTP complies with all applicable requirements for letter contracts set forth in the FAR and the requirements of this section, includes all relevant provisions and clauses, and that all actual or potential conflict of interest or other contracting issues are identified and resolved prior to NTP issuance. To assist the EPA on-scene coordinator and EPA FCS 1102 contracting officer in their responsibilities regarding NTP award, an NTP checklist will be completed by the EPA FCS 1102 contracting officer or EPA onscene coordinator prior to issuance of the NTP.

(e) What happens after an NTP is awarded to a contractor? (1) If an NTP is issued by a duly authorized EPA onscene coordinator with a delegation of procurement authority, he or she must notify the cognizant EPA FCS 1102 contracting officer of the NTP award, and provide the NTP checklist to the contracting officer, as soon as possible but

in no event later than the next working day after NTP issuance.

(2) Within 5 working days of the EPA on-scene coordinator's award of an NTP, the on-scene coordinator shall provide to the cognizant EPA FCS 1102 contracting officer all NTP documents, materials, and information necessary for the contracting officer to definitize the contract, and should retain a copy for his/her records. An EPA FCS 1102 contracting officer will be responsible for definitization of the NTP consistent with the definitization procedures set forth in this subpart. During the process of definitizing the NTP, the EPA FCS 1102 contracting officer will send the contractor the "Representations, Certifications, and Other Statements of Offerors" for completion. The contractor will complete this information, and any other required information, and submit it to the EPA FCS 1102 contracting officer prior to definitization of the NTP.

(f) The CCO, who is authorized by EPAAR 1516.603-3 to make the determination to use a letter contract, shall make a class determination and findings authorizing EPA FCS 1102 contracting officers and duly authorized EPA on-scene coordinators with delegations of procurement authority to award NTPs pursuant to the conditions set forth in this subpart.

[66 FR 12900, Mar. 1, 2001]

[blocks in formation]
[blocks in formation]

1517.207 Exercise of options.

(a) Unless otherwise approved by the Chief of the Contracting Office, contracts for services employing option periods shall require that a preliminary written notice of the Government's intention to exercise the option be furnished to the Contractor a minimum of sixty (60) calendar days prior to the date for the exercise of the option. Failure to provide such preliminary notice within the timeframe established in the contract waives the Government's right to unilaterally exercise the option and requires the negotiation of a bilateral contract modification in order to extend the period of performance, where such an extension is authorized.

(b) When the term of the service contract coincides with the fiscal year and delays in receipt of authority to obligate funds for the new fiscal year are anticipated, the Contracting Officer, if the contract so provides (see FAR 17.204(d)), may, within 60 days after the end of the fiscal year, unilaterally exercise an option to extend the term of the contract. The option may be exercised only if funds become available within the 60-day period. In the event that sufficient funding is not available within the 60 day period, the Government waives the right to exercise the option, thereby rendering any additional requirements subject to full and open competition requirements.

(c) The Contracting Officer, if the contract so provides, may, subject to the conditions in FAR 17.204(d), 32.7032, and 32.705-1(a), exercise an option contingent upon the availability of funds. To exercise such an option, the contract must contain the clause in FAR 52.232-18, Availability of Funds. Under no circumstances shall any action be taken which could be construed as creating a legal liability on the part