| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 820 pages
...plaintiff can escape the requirement that "Any claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...by the contractor of the notification of change," and the requirement that any disputes concerning a question of fact resulting from the change shall... | |
| 1982 - 532 pages
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as result of a change is included in the Contractor's... | |
| 1982 - 690 pages
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| 1983 - 780 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| 1967 - 686 pages
...Any claim by the contractor for an adjustment under this clause must be asserted in writing within 30 days from the date of receipt by the contractor...any time prior to final payment under this contract. A failure to agree on an equitable adjustment under this clause shall be deemed to be a dispute within... | |
| 1970 - 670 pages
...shall be modified In writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...upon any such claim asserted at any time prior to «in«i payment tinder this contract. Where the cost of property made obsolete or excess as a result... | |
| 1980 - 874 pages
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...receive and act upon any such claim asserted at any time pi.tr to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning... | |
| 1972 - 220 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
| |