Handbook of Heavy Construction, Volume 1Frank Whitworth Stubbs McGraw-Hill, 1959 - 700 pages |
From inside the book
Results 1-3 of 90
Page 8-13
... aggregate c . Moisture content of 12- to 3 - in . aggregate = 0.5 per cent = 1.0 per cent 1.5 per cent d . Moisture content of 34- to 12 - in . aggregate e . Moisture content of No. 4 to 34 - in . aggregate = f . 0.15 gal of air ...
... aggregate c . Moisture content of 12- to 3 - in . aggregate = 0.5 per cent = 1.0 per cent 1.5 per cent d . Moisture content of 34- to 12 - in . aggregate e . Moisture content of No. 4 to 34 - in . aggregate = f . 0.15 gal of air ...
Page 9-10
... aggregate ( 1 ) Processed . ( 2 ) Unprocessed . 4. Mixture proportioning studies ( per mixture ) a . 34 - in . aggregate mixture .. b . 12 - in . aggregate mixture . c . 3 - in . aggregate mixture .. d . 6 - in . aggregate mixture ...
... aggregate ( 1 ) Processed . ( 2 ) Unprocessed . 4. Mixture proportioning studies ( per mixture ) a . 34 - in . aggregate mixture .. b . 12 - in . aggregate mixture . c . 3 - in . aggregate mixture .. d . 6 - in . aggregate mixture ...
Page 9-26
... aggregate . Note : A study of tests for the determination of soft pieces in aggregate gave as a con- clusion that the scratch - hardness test using a hard yellow brass scribe was the only one considered suitable for laboratory and field ...
... aggregate . Note : A study of tests for the determination of soft pieces in aggregate gave as a con- clusion that the scratch - hardness test using a hard yellow brass scribe was the only one considered suitable for laboratory and field ...
Contents
Introduction | 1-4 |
Earthmoving Principles | 1-16 |
E O MARTINSON | 2-2 |
Copyright | |
34 other sections not shown
Common terms and phrases
ammonia application ASTM bars blasting caps bolts bottom bracing bridge bucket cable cableway caisson capacity cement cent coarse aggregate cofferdam concrete construction contract Contractor cost crane crusher cutting edge determined diameter dragline dredging drill driving dump electrode equipment erection estimated excavation explosives factor factor of safety falsework forms girder grade gravel grout hammer handling hoist holes horsepower impact wrench joint length Limestone load machine manufacturers material maximum method nozzle operation Owner oxyacetylene pier pipe placed plant plate posttensioning precast pressure Prestressed Concrete prestressing pugmill pump reinforcing Resident Engineer resistance rock sand scraper screen seal shaft sheet piles shovel side soil specifications speed steel strength stress structure surface Table tendon timber tire tons tower tractor tremie truck tunnel usually vertical walls water-cement ratio weight welding wellpoint wire