Neither the final payment nor any part of the retained percentage shall become due until the Contractor, if required, shall deliver to the Owner a complete release of all liens arising out of this contract, or receipts in full in lieu thereof and, if... Water Works Practice - Page 726by American Water Works Association - 1925 - 790 pagesFull view - About this book
| Clinton Hamlin Blake - 1916 - 360 pages
...above grounds are removed certificates shall at once be issued for amounts withheld because of them. a complete release of all liens arising out of this...and, if required in either case, an affidavit that the releases and receipts include all the labor and material for which a lien might be filed; but the... | |
| Calvin Frank Allen - 1917 - 468 pages
...withheld because of them. Art. 29. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the Contractor,...and, if required in either case, an affidavit that the releases and receipt include all the labor and material for which a lien might be filed ; but the... | |
| 1917 - 550 pages
...withheld because of them. Art. 29. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the Contractor,...and, if required in either case, an affidavit that the releases and receipts include all the labor and material for which a lien might be filed ; but... | |
| Calvin Frank Allen - 1917 - 472 pages
...withheld because of them. Art. 29. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the Contractor,...and, if required in either case, an affidavit that the releases and receipt include all the labor and material for which a lien might be filed ; but the... | |
| 1919 - 476 pages
...withheld because of them. Art. 29. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the Contractor,...and, if required in either case, an affidavit that the releases and receipts include all the labor and material for which a lien might be filed ; but... | |
| Theodore Crane - 1927 - 718 pages
...agreement or arbitration. Art. 32. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the Contractor,...shall deliver to the Owner a complete release of all hens arising out of this Contract, or receipts in full in lieu thereof and, if required in either case,... | |
| Charles Francis Dingman - 1928 - 240 pages
...the fulfilment of this contract. Liens. — Neither the final payment nor any part of the retained percentage shall become due until the contractor,...arising out of this contract, or receipts in full lieu thereof and, if required, in either case, an affidavit that the release and receipts include all... | |
| Lebert Howard Weir, National Recreation Association - 1928 - 552 pages
...right to file and maintain a mechanic's Hen. (b) Neither the final payment nor any part of the retained percentage shall become due until the contractor, if required, shall deliver to the commissioners a complete release of all liens arising out of this contract, or receipts in full in... | |
| |