Owner may, upon ten days' written notice, sell such materials at auction or at private sale and shall account for the net proceeds thereof, after deducting all the costs and expenses that should have been borne by the Contractor. Water Works Practice - Page 723by American Water Works Association - 1925 - 790 pagesFull view - About this book
| Clinton Hamlin Blake - 1916 - 360 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work.—If the Architect deems it inexpedient to correct work injured... | |
| 1917 - 550 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work. — If the Architect deems it inexpedient to correct work... | |
| Calvin Frank Allen - 1917 - 468 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work. — If the Architect deems it inexpedient to correct work... | |
| Calvin Frank Allen - 1917 - 472 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 16. Deductions for Uncorrected Work. — If the Architect deems it inexpedient to correct work... | |
| Calvin Frank Allen - 1919 - 486 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 16. Deductions for Uncorrected Work. — If the Architect and Owner deem it inexpedient to correct... | |
| 1919 - 476 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work. — If the Architect deems it inexpedient to correct work... | |
| American Institute of Architects - 1920 - 212 pages
...not pay the expense of such removal within five days thereafter, the Owner may, upon ten days written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work. — If the Architect and Owner deem it inexpedient to correct... | |
| Saul Gordon - 1923 - 980 pages
...pay the expense of such removal within five days thereafter, the Owner may, upon ten days' written notice, sell such materials at auction or at private...should have been borne by the Contractor. Article 15. Deductions for .Uncorrected Work: — If the Architect and Owner deem it inexpedient to correct... | |
| Clinton H. Blake (Jr) - 1924 - 264 pages
...not pay the expense of such removal within five days thereafter, the Owner may, upon ten days written notice, sell such materials at auction or at private...expenses that should have been borne by the Contractor. Art. 15. Deductions for Uncorrected Work. — If the Architect and Owner deem it inexpedient to correct... | |
| Perley F. Walker - 1924 - 380 pages
...expense of such removal within reasonable time thereafter, the Company may, upon ten days' written notice, sell such materials at auction or at private...costs and expenses that should have been borne by the Constructor. G 14 G 13 ARTICLE X Deductions for Uncorrected Work If the Chief Engineer deems it inexpedient... | |
| |