Environmental Administrative Decisions: Decisions of the United States Environmental Protection Agency, Volume 13U.S. Environmental Protection Agency, 2006 |
From inside the book
Results 1-5 of 100
Page 10
... establishing the BACT limits and IEPA's rationale for rejecting consideration of certain other alternatives to the ... establish that review of a permit is warranted , section 124.19 ( a ) requires that a petitioner both state VOLUME ...
... establishing the BACT limits and IEPA's rationale for rejecting consideration of certain other alternatives to the ... establish that review of a permit is warranted , section 124.19 ( a ) requires that a petitioner both state VOLUME ...
Page 20
... establish clear error and thus to require re- mand of IEPA's permitting decision . We find it significant that all parties here , including Petitioners , agree that Congress intended the permit applicant to have the prerogative to ...
... establish clear error and thus to require re- mand of IEPA's permitting decision . We find it significant that all parties here , including Petitioners , agree that Congress intended the permit applicant to have the prerogative to ...
Page 42
... business advantage in the market place , events that do not warrant exceptions from compliance with a PSD permit . " Id . Petitioners ' arguments , however , do not establish grounds VOLUME 13 42 ENVIRONMENTAL ADMINISTRATIVE DECISIONS.
... business advantage in the market place , events that do not warrant exceptions from compliance with a PSD permit . " Id . Petitioners ' arguments , however , do not establish grounds VOLUME 13 42 ENVIRONMENTAL ADMINISTRATIVE DECISIONS.
Page 43
... establish grounds for review and therefore must fail . We reject Petitioners ' argument that the limited authorization for burning off - site washed coal during periods of extended interruption in the mine - mouth coal supply is overly ...
... establish grounds for review and therefore must fail . We reject Petitioners ' argument that the limited authorization for burning off - site washed coal during periods of extended interruption in the mine - mouth coal supply is overly ...
Page 47
... established grounds for us to grant review of IEPA's permitting decision based on these two distinct , yet related issues ... establish- ing the BACT emission limit . Project Summary at 9. In analyzing the proposed SO2 control technology ...
... established grounds for us to grant review of IEPA's permitting decision based on these two distinct , yet related issues ... establish- ing the BACT emission limit . Project Summary at 9. In analyzing the proposed SO2 control technology ...
Other editions - View all
Common terms and phrases
administrative Agency Agency's air quality ALJ's alleged appeal application argument asbestos BACT analysis BACT limits Board Brief capacitors Christian County citing clear error coal compliance schedule concluded ConocoPhillips considered count D.C. Cir determination draft permit effluent limits emissions limits enforcement Environmental EPA's EPS's Euclid explained failed federal FIFRA filed Final Permit hazardous waste Howmet IEPA IEPA's IEPA's response impacts Indeck Init Initial Decision issue LTCP major stationary source Martex ment monitoring NAAQS NPDES NPDES permit NSR Manual OCS source PCB waste Penalty Policy permit decision permit issuer pesticide Petition Petitioners argue pollutant Prairie State's proposed Facility protection PSD permit public comment period RCRA record Region regulatory remand requirements Response to Comments Sierra Club SMRO specifically spent material tion U.S. EPA violations WASA water quality standards