Environmental Administrative Decisions: Decisions of the United States Environmental Protection Agency, Volume 13U.S. Environmental Protection Agency, 2006 |
From inside the book
Results 1-5 of 100
Page 1
... IEPA " ) issued to Prairie State Generating Com- pany , LLC ( " Prairie State " ) authorizing the construction of ... IEPA's determinations of the " best available control technology " emissions limits ( " BACT " ) for sulfur dioxide ...
... IEPA " ) issued to Prairie State Generating Com- pany , LLC ( " Prairie State " ) authorizing the construction of ... IEPA's determinations of the " best available control technology " emissions limits ( " BACT " ) for sulfur dioxide ...
Page 2
... IEPA took a sufficiently hard look at the Facility to determine whether further emissions reductions would be achievable while still meeting Prairie State's purpose . The Board rejects Petitioners ' argument that IEPA erred as a matter ...
... IEPA took a sufficiently hard look at the Facility to determine whether further emissions reductions would be achievable while still meeting Prairie State's purpose . The Board rejects Petitioners ' argument that IEPA erred as a matter ...
Page 3
... IEPA's permit limit . IEPA did consider , prior to issuing its decision , information substantially similar to the new information upon which Petitioners rely . The Board rejects Petitioners ' contention that IEPA provided no record ...
... IEPA's permit limit . IEPA did consider , prior to issuing its decision , information substantially similar to the new information upon which Petitioners rely . The Board rejects Petitioners ' contention that IEPA provided no record ...
Page 8
... IEPA issued a draft permit , along with a project summary and provided notice to the public inviting comment on the draft permit between February 6 , 2004 , and April 21 , 2004. The public comment period was subse- quently extended ...
... IEPA issued a draft permit , along with a project summary and provided notice to the public inviting comment on the draft permit between February 6 , 2004 , and April 21 , 2004. The public comment period was subse- quently extended ...
Page 9
... IEPA to reconsider its decision after consider- ing both the public comments and IEPA's response to comments . Id . at 7 . On April 28 , 2005 , IEPA issued the permitting decision that is the subject of the present petition for review ...
... IEPA to reconsider its decision after consider- ing both the public comments and IEPA's response to comments . Id . at 7 . On April 28 , 2005 , IEPA issued the permitting decision that is the subject of the present petition for review ...
Other editions - View all
Common terms and phrases
administrative Agency Agency's air quality ALJ's alleged appeal application argument asbestos BACT analysis BACT limits Board Brief capacitors Christian County citing clear error coal compliance schedule concluded ConocoPhillips considered count D.C. Cir determination draft permit effluent limits emissions limits enforcement Environmental EPA's EPS's Euclid explained failed federal FIFRA filed Final Permit hazardous waste Howmet IEPA IEPA's IEPA's response impacts Indeck Init Initial Decision issue LTCP major stationary source Martex ment monitoring NAAQS NPDES NPDES permit NSR Manual OCS source PCB waste Penalty Policy permit decision permit issuer pesticide Petition Petitioners argue pollutant Prairie State's proposed Facility protection PSD permit public comment period RCRA record Region regulatory remand requirements Response to Comments Sierra Club SMRO specifically spent material tion U.S. EPA violations WASA water quality standards