Construction Delay: Responsibilities, Risks, and LitigationCahners Books International, 1976 - 367 pages |
From inside the book
Results 1-3 of 68
Page 7
... amount of material that was to be dredged . Because the amount to be dredged was reduced , the contractor filed a claim for increased overhead per unit to be removed . The court stated : “ The plain- tiff [ contractor ] assumed the risk ...
... amount of material that was to be dredged . Because the amount to be dredged was reduced , the contractor filed a claim for increased overhead per unit to be removed . The court stated : “ The plain- tiff [ contractor ] assumed the risk ...
Page 174
... amount of $ 70,393 because the amount was arrived at with a specific rationale . ( This rationale was accepted by the insurance company previously . ) In Clark v . Ferro ( Reference Case 16 ) , the court ruled that evidence in regard to ...
... amount of $ 70,393 because the amount was arrived at with a specific rationale . ( This rationale was accepted by the insurance company previously . ) In Clark v . Ferro ( Reference Case 16 ) , the court ruled that evidence in regard to ...
Page 251
... amount claimed for alleged extra engineering service , and $ 120,000 , the full amount claimed for delay damages . The balance of the judgment was for interest of $ 15,754.68 and costs . This action was brought by the plumbing ...
... amount claimed for alleged extra engineering service , and $ 120,000 , the full amount claimed for delay damages . The balance of the judgment was for interest of $ 15,754.68 and costs . This action was brought by the plumbing ...
Other editions - View all
Common terms and phrases
action actual additional Aetna agreed agreement alleged amount appeal approval arbitration architect award basic basis borrow pits breach of contract building caused change orders City City of Littleton clause Commissioner Company complaint construction contract contracting officer coordination Corp counsel County court found court held curtainwall damages for delay defendant defendant's delay claim delay damages dispute documents drawings duress Egan engineer evidence extension of contract extra fact failure Fenestra Hammermill Hancock HVAC imposed included installation involved jury liquidated damages litigation material method Obata and Kassabaum owner parties payment percent performance Peter Kiewit Sons plaintiff plans and specifications plumbing prime contractor progress quantum meruit question reasonable recover Reference refused responsible result rule schedule shop drawings subcontractor substantial completion suit supervision Supreme Court tion Town of Poughkeepsie tract tractor trial court United waived waiver York