Construction Delay: Responsibilities, Risks, and LitigationCahners Books International, 1976 - 367 pages |
From inside the book
Results 1-3 of 50
Page 43
... agreement used them when they agreed to them , is the great desideratum and the true end of all contractual interpretation . The express terms of an agreement may not be abrogated , nullified , or modified by parol testimony ; but ...
... agreement used them when they agreed to them , is the great desideratum and the true end of all contractual interpretation . The express terms of an agreement may not be abrogated , nullified , or modified by parol testimony ; but ...
Page 167
... agreement to arbitrate that precludes redress in the courts is against public policy and illegal . Therefore , an agreement to arbitrate in the common law base for the laws in this country is not enforceable and would not constitute or ...
... agreement to arbitrate that precludes redress in the courts is against public policy and illegal . Therefore , an agreement to arbitrate in the common law base for the laws in this country is not enforceable and would not constitute or ...
Page 238
... agreement . After the supplemental agreement was executed , the contractor made numerous requests for details regarding reconstruction without receiving the requested additional details in writing . On April 15 , 1962 , the contractor ...
... agreement . After the supplemental agreement was executed , the contractor made numerous requests for details regarding reconstruction without receiving the requested additional details in writing . On April 15 , 1962 , the contractor ...
Other editions - View all
Common terms and phrases
action actual additional Aetna agreed agreement alleged amount appeal approval arbitration architect award basic basis borrow pits breach of contract building caused change orders City City of Littleton clause Commissioner Company complaint construction contract contracting officer coordination Corp counsel County court found court held curtainwall damages for delay defendant defendant's delay claim delay damages dispute documents drawings duress Egan engineer evidence extension of contract extra fact failure Fenestra Hammermill Hancock HVAC imposed included installation involved jury liquidated damages litigation material method Obata and Kassabaum owner parties payment percent performance Peter Kiewit Sons plaintiff plans and specifications plumbing prime contractor progress quantum meruit question reasonable recover Reference refused responsible result rule schedule shop drawings subcontractor substantial completion suit supervision Supreme Court tion Town of Poughkeepsie tract tractor trial court United waived waiver York