River; activities of the California Debris Commission; administration of laws pertaining to preservation of navigable waters; surveys and charting of northern and northwestern lakes and connecting waters; clearing and straightening channels; removal of obstructions to navigation; and rescue work, and repair, or restoration of flood control projects threatened or destroyed by flood; $138,397,000, to remain $138, 397, 000 available until expended.

[For an additional amount for 1962, for the foregoing purpose, see p. 216.]

GENERAL EXPENSES

For expenses necessary for general administration and related functions in the Office of the Chief of Engineers and offices of the Division Engineers; activities of the Board of Engineers for Rivers and Harbors and the Beach Erosion Board; commercial statistics; and miscellaneous investigations; $13,148,000.

FLOOD CONTROL, MISSISSIPPI RIVER AND TRIBUTARIES

For expenses necessary for prosecuting work of flood control, and rescue work, repair, restoration, or maintenance of flood control projects threatened or destroyed by flood, as authorized by law (33 U.S.Č. 702a, 702g-1), $72,950,000, to remain available until expended..

UNITED STATES SECTION, SAINT LAWRENCE RIVER JOINT BOARD OF

ENGINEERS

For necessary expenses of the United States section of the Saint Lawrence River Joint Board of Engineers, established by Executive Order 10500, dated November 4, 1953, including services as authorized by section 15 of the Act of August 2, 1946 (5 U.S.C. 55a), at rates not to exceed $100 per day for individuals; $20,000: Provided, That no part of these funds shall be obligated until agreement has been entered into, by the United States Government and the United States entity authorized to construct the power works in the International Rapids section of the Saint Lawrence River, providing for the reimbursement of the expenditures of the United States section of this Board by the construction entity.

INTERNATIONAL NAVIGATION CONGRESSES

For necessary expenses of the meeting of the Permanent International Association of Navigation Congresses to be held in the United States in 1961, as authorized by law (72 Stat. 513), $30,000-

ADMINISTRATIVE PROVISIONS

Appropriations in this title shall be available for expenses of attendance by military personnel of meetings in the manner authorized by section 19 (b) of the Act of July 7, 1958 (72 Stat. 336), uniforms, or allowances therefor, as authorized by the Act of September 1, 1954, as amended (5 U.S.C. 2131), and for printing, either during a recess or session of Congress, of survey reports authorized by law, and such. survey reports as may be printed during a recess of Congress shall be printed, with illustrations, as documents of the next succeeding session of Congress; and during the current fiscal year the revolving fund, Corps of Engineers, shall be available for purchase (not to exceed one hundred and sixty-six, of which one hundred and forty-eight shall be for replacement only) and hire of passenger motor vehicles. [Total, Corps of Engineers-civil, $964,443,880.]

Total, title I, civil functions, Department of the Army, $974,883,880.]

13, 148, 000

72, 950,000

20,000

30,000.

TITLE II-DEPARTMENT OF THE INTERIOR

BUREAU OF RECLAMATION

For carrying out the functions of the Bureau of Reclamation as provided in the Federal reclamation laws (Act of June 17, 1902, 32 Stat. 388, and Acts amendatory thereof or supplementary thereto) and other Acts applicable to that Bureau, as follows:

GENERAL INVESTIGATIONS

For engineering and economic investigations of proposed Federal reclamation projects and studies of water conservation and development plans and activities preliminary to the reconstruction, rehabilitation and betterment, financial adjustment, or extension of existing projects, including not to exceed $350,000 for investigations of projects in Alaska, to remain available until expended, $6,643,000, of which $5,520,000 shall be derived from the reclamation fund and $500,000 shall be derived from the Colorado River development fund: Provided, That none of this appropriation shall be used for more than one-half of the cost of an investigation requested by a State, municipality, or other interest: Provided further, That $250,000 of this appropriation shall be transferred to the United States Fish and Wildlife Service for studies, investigations, and reports thereon as required by the Fish and Wildlife Coordination Act of 1958 (72 Stat. 563-565) to provide that wildlife conservation shall receive equal consideration and be coordinated with other features of water-resource development programs of the Bureau of Reclamation.

CONSTRUCTION AND REHABILITATION

For construction and rehabilitation of authorized reclamation projects or parts thereof (including power transmission facilities) and for other related activities, as authorized by law, to remain available until expended, $152,405,500, of which $67,400,000 shall be derived from the reclamation fund: Provided, That no part of this appropriation shall be used to initiate the construction of transmission facilities within those areas covered by power wheeling service contracts which include provision for service to Federal establishments and preferred customers, except those transmission facilities for which construction funds have been heretofore appropriated, those facilities which are necessary to carry out the terms of such contracts or those facilities for which the Secretary of the Interior finds the wheeling agency is unable or unwilling to provide for the integration of Federal projects or for service to a Federal establishment or preferred customer: Provided further, That funds shall be available to complete the construction of and to operate and maintain within and adjacent to the Yuma Irrigation District, in the South Gila Valley, Arizona, those drainage works on which construction has heretofore been initiated pursuant to the Act of June 28, 1946 (60 Stat. 338): Provided further, That not to exceed $192,000 of funds made available for construction and maintenance of access roads in the Yellowtail Unit area shall be nonreimbursable: Provided further, That not to exceed $435,000 shall be available toward investigation and the emergency rehabilitation of the Dalton Gardens, Avondale, and Hayden Lake Unit, Rathdrum Prairie Irrigation projects, Idaho, to be effective only upon approval by the President of H.R. 4458, Eighty-seventh Congress.

$6,643,000

152, 405, 500

OPERATION AND MAINTENANCE

For operation and maintenance of reclamation projects or parts thereof and of other facilities, as authorized by law; and for a soil and moisture conservation program on lands under the jurisdiction of the Bureau of Reclamation, pursuant to law, $36,189,000, of which $30,687,000 shall be derived from the reclamation fund and $1,491,000 shall be derived from the Colorado River Dam fund: Provided, That funds advanced for operation and maintenance of reclamation projects or parts thereof shall be deposited to the credit of this appropriation and may be expended for the same objects and in the same manner as sums appropriated herein may be expended, and the unexpended balances of such advances shall be credited to the appropriation for the next succeeding fiscal year.

LOAN PROGRAM

For loans to irrigation districts and other public agencies for construction of distribution systems on authorized Federal reclamation projects, and for loans and grants to non-Federal agencies for construction of projects, as authorized by the Acts of July 4, 1955, as amended (43 U.S.C. 421a-421d), and August 6, 1956 (43 U.Ś.C. 422a-422k), as amended (71 Stat. 48), including expenses necessary for carrying out the program, $13,272,600, to remain available until expended: Provided, That any contract under the Act of July 4, 1955 (69 Stat. 244), as amended, not yet executed by the Secretary, which calls for the making of loans beyond the fiscal year in which the contract is entered into shall be made only on the same conditions as those prescribed in section 12 of the Act of August 4, 1939 (53 Stat. 1187, 1197).

EMERGENCY FUND

For an additional amount for the "Emergency fund", as authorized by the Act of June 26, 1948 (43 U.S.C. 502), to remain available until expended for the purposes specified in said Act, $1,000,000, to be derived from the reclamation fund.

UPPER COLORADO RIVER BASIN FUND

For the Upper Colorado River Storage Project, as authorized by the Act of April 11, 1956 (43 U.S.C. 620d), to remain available until expended, $55,468,000 of which $52,534,500 shall be available for the "Upper Colorado River Basin Fund" authorized by section 5 of said. Act of April 11, 1956, and $2,933,500 shall be available for construction of recreational and fish and wildlife facilities authorized by section 8 thereof, and may be expended by bureaus of the Department through or in cooperation with State or other Federal agencies, and advances to such Federal agencies are hereby authorized: Provided, That no part of the funds herein appropriated shall be available for construction or operation of facilities to prevent waters of Lake Powell from entering any National Monument.

GENERAL ADMINISTRATIVE EXPENSES

For necessary expenses of general administration and related functions in the offices of the Commissioner of Reclamation and in the regional offices of the Bureau of Reclamation, $9,430,000, to be derived from the reclamation fund and to be nonreimbursable pursuant to the Act of April 19, 1945 (43 U.S.C. 377): Provided, That no part of any other appropriation in this Act shall be available for activities or functions budgeted for the current fiscal year as general administrative expenses.

[blocks in formation]

SPECIAL FUNDS

Sums herein referred to as being derived from the reclamation fund, the Colorado River Dam fund, or the Colorado River development fund, are appropriated from the special funds in the Treasury created by the Act of June 17, 1902 (43 U.S.C. 391), the Act of December 21, 1928 (43 U.S.C. 617a), and the Act of July 19, 1940 (43 U.S.C. 618a), respectively. Such sums shall be transferred, upon request of the Secretary, to be merged with and expended under the heads herein specified; and the unexpended balances of sums transferred for expenditure under the heads “Operation and Maintenance" and "General Administrative Expenses" shall revert and be credited to the special fund from which derived.

ADMINISTRATIVE PROVISIONS

Appropriations to the Bureau of Reclamation shall be available for purchase of not to exceed seventy-four passenger motor vehicles for replacement only; payment of claims for damage to or loss of property, personal injury, or death arising out of activities of the Bureau of Reclamation; payment, except as otherwise provided for, of compensation and expense of persons on the rolls of the Bureau of Reclamation appointed as authorized by law to represent the United States in the negotiation and administration of interstate compacts without reimbursement or return under the reclamation laws; rewards for information or evidence concerning violations of law involving property under the jurisdiction of the Bureau of Reclamation; performance of the functions specified under the head "Operation and Maintenance Administration", Bureau of Reclamation, in the Interior Department Appropriation Act, 1945; preparation and dissemination of useful information including recordings, photographs, and photographic prints; and studies of recreational uses of reservoir areas, and investigation and recovery of archeological and paleontological remains in such areas in the same manner as provided for in the Act of August 21, 1935 (16 U.S.C. 461-467): Provided, That no part of any appropriation made herein shall be available pursuant to the Act of April 19, 1945 (43 U.S.C. 377), for expenses other than those incurred on behalf of specific reclamation projects except "General Administrative Expenses" and amounts provided for reconnaissance, basin surveys, and general engineering and research under the head "General Investigations".

Allotments to the Missouri River Basin project from the appropriation under the head "Construction and Rehabilitation" shall be available additionally for said project for those functions of the Bureau of Reclamation provided for under the head "General Investigations” (but this authorization shall not preclude use of the appropriation under said head within that area), and for the continuation of investigations by agencies of the Department on a general plan for the development of the Missouri River Basin. Such allotments may be expended through or in cooperation with State and other Federal agencies, and advances to such agencies are hereby authorized.

Sums appropriated herein which are expended in the performance of reimbursable functions of the Bureau of Reclamation shall be returnable to the extent and in the manner provided by law.

No part of any appropriation for the Bureau of Reclamation, contained in this Act or in any prior Act, which represents amounts earned under the terms of a contract but remaining unpaid, shall be obligated for any other purpose, regardless of when such amounts are to be paid: Provided, That the incurring of any obligation prohibited by this paragraph shall be deemed a violation of section 3679 of the Revised Statutes, as amended (31 U.S.C. 665).

No funds appropriated to the Bureau of Reclamation for operation and maintenance, except those derived from advances by water users, shall be used for the particular benefit of lands (a) within the boundaries of an irrigation district, (b) of any member of a water users' organization, or (c) of any individual, when such district, organization, or individual is in arrears for more than twelve months in the payment of charges due under a contract entered into with the United States pursuant to laws administered by the Bureau of Reclamation.

Not to exceed $225,000 may be expended from the appropriation "Construction and rehabilitation" for work by force account on any one project or Missouri Basin unit and then only when such work is unsuitable for contract or no acceptable bid has been received and, other than otherwise provided in this paragraph or as may be necessary to meet local emergencies, not to exceed 12 per centum of the construction allotment for any project from the appropriation "Construction and rehabilitation" contained in this Act shall be available for construction work by force account: Provided, That this paragraph shall not apply to work performed under the Rehabilitation and Betterment Act of 1949 (63 Stat. 724).

[Total, Bureau of Reclamation, $274,408,100.]

BONNEVILLE POWER ADMINISTRATION

CONSTRUCTION

After October 1, 1961, the position of Administrator, Bonneville Power Administration, shall have the same annual rate of compensation as that provided for positions listed in section 2205 (b) of title 5, United States Code, so long as held by the present incumbent. For construction and acquisition of transmission lines, substations, and appurtenant facilities, as authorized by law, $20,875,000, to remain available until expended.

OPERATION AND MAINTENANCE

For necessary expenses of operation and maintenance of the Bonneville transmission system and of marketing electric power and energy, $12,205,000__

ADMINISTRATIVE PROVISIONS

Appropriations of the Bonneville Power Administration shall be available to carry out all the duties imposed upon the Administrator pursuant to law. Appropriations made herein to the Bonneville Power Administration shall be available in one fund, except that the appropriation herein made for operation and maintenance shall be available only for the service of the current fiscal year.

Other than as may be necessary to meet local emergencies, not to exceed 12 per centum of the appropriation for construction herein made for the Bonneville Power Administration shall be available for construction work by force account or on a hired-labor basis. [Total, Bonneville Power Administration, $33,080,000.]

SOUTHEASTERN POWER ADMINISTRATION

OPERATION AND MAINTENANCE

For necessary expenses of operation and maintenance of power transmission facilities and of marketing electric power and energy pursuant to the provisions of section 5 of the Flood Control Act of 1944 (16 U.S.C. 825s), as applied to the southeastern power area, $800,000.

$20,875,000

12, 205, 000

800,000

« PreviousContinue »